Find out more about how we have enabled significant water savings through the recovery and treatment of rejected feedwater, reducing the environmental impact of the site in the case study.
Challenge - Water cooling systems are a popular choice for maintaining stable internal temperatures and optimal functionality, but this requires large amounts of water, increasing both environmental impact and operating costs.
Solution - We have helped a data centre facility in the South East of England by supplying a combination of our technologies that addresses both the site's central urban location constraints and the pressing needs of environmental impact and cost reduction.
Outcome - We helped reduce both operational costs and water consumption, minimising the facility’s environmental footprint.